An initial plan for the 237 acre industrial park shows that eight buildings and a detention pond can be built on 144 acres of the parcel. TranSystems’ preliminary engineering study estimated the cost to develop the 144 acres to be about $13 million. The Tonganoxie City Council discussed splitting the plan into three phases to help spread out the cost of the project.